Wind Energy Case Study - Northern Ireland

Panel Installation

WIND TURBINE EQUIPMENT

Coyle Group provided a Safety Officer for a client in Northern Ireland in 2017. The project involved the construction of nine wind turbines on farmland in County Antrim. During the project kick-off meeting it was identified that the Farm Control Unit and SCADA system would not fit through the control room door of the substation.

A BESPOKE REQUIREMENT

A bespoke and safe solution was required to move this delicate equipment into the building and into its final position. This would require the unit to be moved on its side to fit through the door. The unit was far too heavy to be handled manually, so a plan was devised by our Safety Officer on site to do the job safely.

TRIALLING THE SOLUTION

The Safety Officer contacted the relevant client manager to understand all the data from the unit. Once this was available, a replica was developed to mirror the size of the panel. A couple of portable lifting solutions were then trialled on site with the assistance of the contracted hire company. Once the trial was dynamically risk assessed and completed, the Safety Officer put together the required paperwork for the customer to complete and sign off.

BETTER SUBSTATION DESIGNS FOR THE FUTURE

Beyond the immediate challenge on this project, this operation identified a design issue with the substation. The site team on this project learned from the issues and that same site team were in place on the following project. Consultation between our Safety Officer and the Principal Contractors Project Manager ensured that, on the sister site, lessons learned were actioned. The substation door size was changed to reflect the requirements and the unit was simply wheeled into position on a pallet truck.

A SUCCESSFUL LIFT

The required lift of the equipment took place as per the Risk Assessment Method Statement (RAMS) and Lift Plan. The unit was successfully moved into position for the technicians to install.

Examples of Work

Case Studies

Utilities Case Study
Reducing risk when working at height on high voltage transformers Background In 2017, our Coyle Group...
Learn More >
Health & Safety in Engineering Industry Case Study
Six months of rapid health and safety improvements at sub-stations in Ireland Overview Whilst performing the role...
Learn More >
Risk Maturity - Health & Safety Consulting
Industry Leading Framework Reduces Third Party Risks in the Construction Supply Chain THIRD PARTY RISKS Modern...
Learn More >
Health & Safety in the Utilities Industry Case Study
Reducing risk when working at height on high voltage transformers, a case study Background In 2017, our...
Learn More >

Why hire our safety people?

Download the Capability Statement to Discover Why our Safety Officers Are Right For Your Project